Web Links

Contractor Q & A Forum

City of Whitefish

WGM Group

Federal Highway Administration

Central Avenue Project

Aeriel Construction Video

 

Document Links

Newsletter Issue 1- 10/10

Newsletter Issue 2- 01/11

Newsletter Issue 3- 09/11

Comprehensive Project Timeline- 09/10

Categorical Exclusion Environmental Document-12/10

Final Design Roll Drawing- 7/11

Whitefish Downtown Master Plan

TIGER I Grant Application- 2009

 

Contacts

Jeremy Keene P.E.
WGM Group, Project Design & Environmental Engineer
406-728-4611
jkeene@wgmgroup.com

Karin Hilding
City of Whitefish, Senior Project Engineer
406-863-2450
khilding@cityofwhitefish.org

Gary Kalberg, P.E.
Stelling Engineers, Project Construction Manager
406-261-7497 or 406-755-8602 x4
gkalberg@stellinginc.com

Stephen Herzog
CTA, Project Contract Administration Consultant
406-257-8172 x 1510
stephenh@ctagroup.com

Dan Smith
Federal Highway Administration, Recovery Coordinator
(406) 441-3918
dan.smith@dot.gov

Project Updates

Weekly Progress Reports-Fall 2011

Weekly Progress Report 10/25/11

Weekly Progress Report 10/17/11

Weekly Progress Report 10/14/11

Weekly Progress Report 10/6/11

Weekly Progress Report 9/29/11

Weekly Progress Report 9/14/11

----------------------------------------------------------------------------------------------------------------------

Detour Routes- September 7, 2011
Click the links below to view detour routes during fall construction.

Detour Route September 12 through September 15, 2011

Detour Route September 15 through October 1, 2011

----------------------------------------------------------------------------------------------------------------------

Newsletter Issue 3- September 6, 2011
A third newsletter was recently sent out to project stakeholders. In the newsletter there is information regarding:

  • Project Status
  • Traffic and Parking Restrictions During Construction
  • Public Meeting Announcement
  • New Contact Information
  • Detour Route Maps

Click on the image below to download a .PDF of the newsletter.

----------------------------------------------------------------------------------------------------------------------

Contract Award/Public Meeting- September 1, 2011
The City has awarded the Highway 93/2nd Street Improvement Project construction contract to the firm, LHC Inc.  LHC will be responsible for reconstruction of two blocks of Highway 93, from Spokane Avenue to Baker Avenue, including those intersections.  The project will also include sewer improvements to Lupfer Avenue. 


This project will require extensive detours with substantial impacts to downtown traffic. The detour routes will change throughout the job.  Information on the current detour route will be available from the City Public Works Department and Stelling Engineers.  The current detour route map will also be posted on this project website.  Due to the need to detour highway traffic onto City streets there will also be parking restrictions.

There will be a pre-constuction meeting held on Tuesday, September 6th at 1:30 in City Hall Council Chambers.

----------------------------------------------------------------------------------------------------------------------

Project Out For Bidding- July 22, 2011
After a year of an aggressive design schedule, the 2nd Street Improvement Project has received final approval for bidding. Click here to view the Final Design. This downtown streetscape project was originally conceived in the Whitefish Downtown Master Plan. As part of national economic recovery efforts in 2009, the City of Whitefish received a $3.5 million TIGER grant from the US Department of Transportation. Fast tracked design began in August 2010, so funds could be obligated by September 2011, as stipulated in the grant. This would not have been possible without ongoing support from the Heart of Whitefish, the Montana Department of Transportation, and the Federal Highway Administration – all of whose attention to detail and diligence have been extraordinary.


The advertisement to bidders will run in Wednesday, July 27th's, Daily Interlake and Whitefish Pilot. Contractors interested in bidding will find all relevant documents and answers to all questions at the Contractor Question and Answer Forum.

Contractor Question and Answer Forum

----------------------------------------------------------------------------------------------------------------------

Final Design Complete - July 19, 2011
Final Plans and Specifications for the US Highway 93 / 2nd Street Improvement project are complete! The project will go out to bid on Friday, July 22. Click the image below to download a PDF of the Final Design.

----------------------------------------------------------------------------------------------------------------------

Final Design Nearing Completion - June 8, 2011
Final Plans and Specifications for the US Highway 93 / 2nd Street Improvement project will be submitted this week for review by the FHWA, MDT, and City. A Final Design Overview is available for public viewing below, or at the City Public Works Department. This design reflects discussion and decisions made at the April 14, 2011 Design Workshop and subsequent City Council meeting on April 18, 2011. Drawings and markups from those meetings are also available below.

Roll Drawing Final Design Overview

Roll Drawing with Proposed Changes

Roll Drawing with Markups

Design Features Include:

  • decorative street lights with hanging baskets
  • provisions for holiday decorations
  • street trees with metal grates
  • landscaped islands on Central
  • continuous laydown curbs with concrete crosswalks
  • curb extensions
  • colored concrete buffer areas (dark gray)
  • benches, bike racks, and trash receptacles
  • new traffic signals, left turn lanes, and protected phasing 

Complete plans and specifications will be available for viewing on June 13th.

For comments and questions, please contact Emily Brock at ebrock@wgmgroup.com, or 406-728-4611.

----------------------------------------------------------------------------------------------------------------------

Right-of-Way Acquisition Moves Forward, Public Comment Welcome - March 10, 2011

The City of Whitefish is currently negotiating right-of-way acquisition with a number of private landowners. This is expected to be complete by the end of March. Residents and business owners interested in meeting with the designers should contact Emily Brock at 406-728-4611. The team is currently setting up meetings with interested people for March 18, 2011.

----------------------------------------------------------------------------------------------------------------------

Second Public Meeting Held - February 4, 2011

On February 1, 2011 a public meeting was held with residents and merchants in Whitefish to discuss the design of the Highway 93/2nd Street Improvements Project. Click on the above graphics to view displays from the public meeting.

Engineers will take every comment into account as they design the project details. Important discussion items were:

-Maintaining Parking
-Pedestrian Friendly Crosswalks
-Landscaping
-Left Turn Signals
-Turn Lane Length
-Construction Implementation

The time for public comment is not over! Stakeholders for this project are encouraged to weigh in over the coming months and this site will remain up-to-date as decisions are made. To contact the engineers call Emily Brock at 406-728-4611. To recieve up-to-date notifications please email Emily at ebrock@wgmgroup.com.

Meeting minutes for the February 1st meeting are available by clicking here. Comments recieved at the Meeting are available by clicking here.

 

----------------------------------------------------------------------------------------------------------------------

Newsletter Issue 2 - January 20, 2011

A second newsletter was recently sent out to project stakeholders. It includes a preliminary design overview as well as status updates and a comment sheet. Click on the image below to download an .PDF copy of the newsletter.

----------------------------------------------------------------------------------------------------------------------

Public Meeting Announcement - January 5, 2011

City Council Chambers, 402 E. 2nd Street

----------------------------------------------------------------------------------------------------------------------

Updates for US Highway 93/2nd Street Improvements Project - December 20, 2010

Progress for this project is steady and on track with the tight timeline. Click here for the comprehensive timeline.

Recent Progress
  • The Environmental Document is complete and has been submitted for Federal Highway Administration approval. We expect anticipate it will be signed before the end of the year.
  • The Preliminary 30% Plan and Design Report has been submitted to the City of Whitefish, the Montana Department of Transportation, and the Federal Highway Administration for review.
  • Initial discussions with affected landowners on proposed right-of-way have begun.

Next Step

Feedback from City, State, and Federal agencies as well as from the general public on the 30% Preliminary Design is an important part of the process. A second Public Meeting and round of stakeholder meetings is planned for mid-January. It is important that stakeholders attend this meeting to keep the schedule on-track. There will be a presentation on the preliminary design and time for public comment. Look for a meeting announcement after the first of the year.

Steps After the January Public Meeting

  • Begin formal right-of-way acquisition process
  • Incorporate review comments and begin Final Design

New Public Documents

----------------------------------------------------------------------------------------------------------------------

First Public Meeting a Success - October 15, 2010

A successful public meeting was held on Thursday October 14, 2010 in Whitefish to address the 2nd Avenue Street Improvements Project. The design team received feedback about the conceptual design, which came out of the Whitefish Master Plan, from about 30 interested residents, stakeholders, and business owners. The citizens of Whitefish came well informed and were skilled at communicating their concerns. Click here to view the newsletter that was passed out at the meeting, including conceptual design.


Besides aiding design, the Whitefish Master Plan helped the community recieve the $3.5 Million TIGER Grant, which makes this project possible. Because funding comes from this source, the timeline for design is short. This means residents should speak up now, instead of down the line.


The next public meeting will be held in January. Citizens are welcome to contact designers or the City of Whitefish staff in the mean time to discuss the project.

----------------------------------------------------------------------------------------------------------------------

Project Description - September 2010

The Whitefish Downtown Business District was originally constructed in early 1900’s.  While many downtown buildings have been renovated and modernized, much of the public infrastructure is in poor condition and beyond its useful life. This project will improve traffic flow on U.S. Highway 93 in, around, and through downtown Whitefish.

This project will reconstruct two blocks of U.S. Highway 93 in downtown Whitefish, from Spokane Avenue to Baker Avenue including those intersections and transitions beyond the intersections. Improvements include reconstruction of the roadway and adjacent sidewalks; reconstruction of underground utilities within the right-of-way; new streetlights; new highway signage; and the installation of new traffic signals.

The project is funded through a TIGER (Transportation Investment Generating Economic Recovery) Discretionary Grant that has been awarded to the City of Whitefish by the U.S. Department of Transportation. This grant program is administered under Title XII of the American Recovery and Reinvestment Act of 2009 (ARRA) and requirements of the Act do apply.

----------------------------------------------------------------------------------------------------------------------

Public Involvement - September 2010

Public involvement continues to be a priority for the City of Whitefish.

Public Meeting #1: October 14, 2010 in City Council Chambers, 402 E. 2nd Street. Open house to begin at 5:30pm, presentation to begin at 6:00pm.

   